Press Release – Bitdeer Announces July 2024 Production and Operations Update
|
Bitdeer Technologies Group
|
||
By:
|
/s/ Jihan Wu
|
|
Name:
|
Jihan Wu
|
|
Title:
|
Chief Executive Officer
|
|
Date: August 5, 2024 |
•
|
Self-mined Bitcoin: Mined 181 Bitcoins.
|
•
|
Mining Rigs R&D:
|
•
|
Mass production is on track for SEAL01 chips and SEALMINER A1 series mining rigs, including both air cooling and hydro cooling.
|
•
|
Taiwan Semiconductor Manufacturing Company (TSMC)’s delivery of SEAL02 initial tape-out wafers is anticipated for late September 2024. If the testing is successful, mass production is scheduled to commence by the end of 2024.
|
•
|
R&D of SEAL03, our third-generation chip, is ongoing.
|
•
|
HPC/AI:
|
•
|
AI cloud services powered by NVIDIA DGX SuperPOD with H100 system reached 100% utilization during the month of July. We will expand our AI cloud operation carefully to capture the opportunities while
avoiding over investment.
|
•
|
Engaged with TLM Group, a leading consultant in HPC/AI datacenter engineering and construction, to conduct comprehensive research on Bitdeer’s sites and advise on a broader datacenter strategy, including co-location, joint- ventures
and other monetization options.
|
•
|
Mining datacenters
|
•
|
Tydal, Norway phase 1 and phase 2 site expansions remain on track to energize 40 MW in Q4 2024 and 135 MW by mid-2025.
|
•
|
Bhutan Jigmeling 500MW substation is expected to be completed by Q1 2025.
|
•
|
We commenced upgrading a portion of the Rockdale, Texas mining datacenter into hydro cooling, which we expect to be complete in Q4 2024. We believe such investment will not only benefit our Bitcoin mining business but also can be used
for HPC/AI infrastructure in the future.
|
•
|
Ohio Edison 221MW project is in the design and long lead time equipment procurement stage.
|
•
|
Planning to deploy 3.4 EH/s of first generation Bitdeer SEALMINERs into Texas, U.S.A. and Tydal, Norway sites in Q4 2024, bringing total proprietary hashrate to 11.8 EH/s.
|
Metrics
|
July 2024
|
June 2024
|
July 2023
|
Total hash rate under management1 (EH/s)
|
21.2
|
22.3
|
20.6
|
- Proprietary hash rate
|
8.6
|
8.5
|
7.9
|
• Self-mining
|
7.5
|
7.3
|
3.8
|
• Cloud Hash Rate
|
1.1
|
1.2
|
1.6
|
- Hosting
|
12.6
|
13.8
|
12.7
|
Mining machines under management
|
212,000
|
223,000
|
215,000
|
- Self-owned2
|
87,000
|
86,000
|
85,000
|
- Hosted
|
125,000
|
137,000
|
130,000
|
Bitcoin mined (self-mining only)
|
181
|
179
|
220
|
•
|
Self-mining refers to cryptocurrency mining for the Company’s own account, which allows it to directly capture the high appreciation potential of cryptocurrency.
|
•
|
Cloud Hash Rate offers hash rate subscription plans and shares mining income with customers under certain arrangements. The Cloud Hash Rate stated above reflects the contracted hash rate with
customers at month-end. However, throughout the month, the Cloud Hash Rate may transition to Self-mining hash rate if customers opt to not make their monthly electricity payments for various reasons.
|
•
|
Hosting encompasses a one-stop mining machine hosting solution including deployment, maintenance, and management services for efficient cryptocurrency mining.
|
•
|
Demolition work started on August 1, 2024.
|
•
|
Cooling system design completed and waiting to begin construction. Equipment procurement is ongoing.
|
•
|
Water Tower testing will begin in August 2024.
|
•
|
Energization timeline to occur in phases throughout Q4 2024.
|
•
|
Buildings and groundwork have been completed, along with the construction of the transformer foundation and housing.
|
•
|
Orders for the procurement of the transformer and electrical equipment have been placed, with delivery and installation currently in progress. Additionally, the procurement and delivery of containers and hydro-cooling systems are
underway, and the construction of drainage systems is ongoing.
|
•
|
Construction of the substation is ongoing and expected to be completed by the end of October 2024.
|
•
|
Energization timeline for the Tydal, Norway Expansion Phase 1 of 40 MW remains on track for Q4 2024.
|
•
|
Substation conceptual design is complete and long lead-time electrical equipment for the substation has been ordered.
|
•
|
Engineering, Procurement, and Construction (EPC) contractor selected for the substation construction.
|
•
|
Civil work is ongoing, with the majority expected to be completed by the end of Q4 2024. Building design is complete, and construction is anticipated to begin in Q1 2025.
|
•
|
Estimated energization timeline remains on track for mid-to-late 2025.
|
•
|
Civil work is nearly completed with an anticipated completion date by the end of September 2024. Construction of transformer and container foundations is in progress and will be completed in phases, with the last phase expected by the
end of February 2025.
|
•
|
132kv/140MW substation design completed, 220kv/360MW substation design in progress. Construction of the substation is anticipated to be ready by the end of Q1 2025.
|
•
|
Procurement of transformers and electrical equipment has been completed, with delivery and installation to be completed in phases over the next two quarters.
|
•
|
Procurement and delivery of containers and hydro-cooling systems are in progress, with completion in phases by the end of Q1 2025.
|
Site / Location
|
Capacity (MW)
|
Status
|
Timing3
|
Energized capacity
|
|||
Rockdale, Texas
|
563
|
Online
|
Completed
|
Knoxville, Tennessee
|
86
|
Online
|
Completed
|
Wenatchee, Washington
|
13
|
Online
|
Completed
|
Molde, Norway
|
84
|
Online
|
Completed
|
Tydal, Norway
|
50
|
Online
|
Completed
|
Gedu, Bhutan
|
100
|
Online
|
Completed
|
Total energized capacity
|
895
|
||
Pipeline capacity
|
|||
Tydal, Norway Phase 1
|
40
|
In progress
|
Q4 2024
|
Tydal, Norway Phase 2
|
135
|
In progress
|
Mid 2025
|
Massillon, Ohio
|
221
|
In progress
|
Mid-to-late 2025
|
Clarington, Ohio Phase 1
|
266
|
In progress
|
Q3 2025
|
Clarington, Ohio Phase 2
|
304
|
Pending approval
|
Estimate 2026
|
Jigmeling, Bhutan
|
500
|
In progress
|
Mid-Late 2025
|
Rockdale, Texas
|
179
|
In planning
|
Estimate 2026
|
Total pipeline capacity
|
1,645
|
||
Total global contracted capacity
|
2,540
|
3 |
Indicative timing. All timing references are to calendar quarters and years.
|
•
|
Aug 19 – 20: Rosenblatt 4th Annual Technology Summit: The Age of AI (Virtual)
|
•
|
Sep 9 – 11: H.C. Wainwright 26th Annual Global Investment Conference in New York City
|
•
|
Nov 14: Cantor Crypto, Digital Assets & AI Infrastructure Conference in Miami
|