Press Release – Bitdeer Announces September 2024 Production and Operations Update
|
Bitdeer Technologies Group
|
||
By:
|
/s/ Jihan Wu
|
|
Name:
|
Jihan Wu
|
|
Title:
|
Chief Executive Officer
|
|
Date: October 3, 2024
|
• |
Self-mined Bitcoin: 164 Bitcoins.
|
• |
Mining Rig Manufacturing and R&D:
|
o |
SEALMINER A1 mass production remains on schedule for Q4 2024 and is expected to contribute 3.4 EH/s to Bitdeer’s proprietary hashrate. Deployment will align with the energization of the Texas hydro-cooling conversion and Tydal, Norway
phase 1 in late Q4 2024 and early Q1 2025.
|
o |
SEAL02 chip initial tape-out wafers were received from TSMC in mid-September. Initial verification and prototype testing indicated a 13.5 J/TH efficiency, while running at low voltage, ultra power-saving mode.
|
o |
SEAL02 chips will be integrated into Bitdeer’s SEALMINER A2 mining machines, with mass production scheduled to commence in November 2024.
|
o |
Design of SEAL03, Bitdeer’s third-generation chip, remains on track to tape-out in Q4 2024 with a chip efficiency of 10 J/TH.
|
• |
HPC/AI:
|
o |
TLM Group successfully completed its feasibility assessment of Bitdeer’s Massillon and Clarington/Hannibal sites in Ohio, reporting largely positive results regarding their suitability for Tier 3 HPC/AI datacenters, due to the
availability of land, power, fiber and water resources. The Company has commenced discussions with development partners and potential end users for these sites.
|
o |
TLM Group’s feasibility assessments of Bitdeer’s other global sites is ongoing.
|
o |
Bitdeer AI cloud services powered by NVIDIA DGX SuperPod with H100 systems remained near 100% average utilization for this month.
|
o |
Launched pilot H100 capacity in Canada, further expanding Bitdeer’s global GPU service offerings and aims to enhance the availability and scalability of high-performance cloud computing resources for customers, supporting AI training,
inference, and various computationally intensive applications.
|
o |
Launched AI Workflow platform, providing quick model inference capabilities.
|
• |
Hosting:
|
o |
Client-hosted mining machine numbers remained steady from August, with the overall hash rate increase of 0.3 EH/s due to improved mix of newly hosted, higher-efficiency machines in Texas. The Company expects the remaining excess capacity
to be filled over the next two quarters with new customers’ machines and Bitdeer’s SEALMINERs for self-mining starting in September 2024 and continuing through Q1 2025.
|
• |
Mining Datacenters:
|
o |
Construction of the Tydal, Norway, 40 MW phase 1 expansion remains on track to be energized in December 2024.
|
o |
Rockdale, Texas, USA, 100 MW hydro-cooling conversion is planned for phased completion between December 2024 and February 2025.
|
o |
Jigmeling, Bhutan, 500 MW construction remains on track with the primary substation expected to be completed by Q1 2025.
|
Metrics
|
Sep 2024
|
Aug 2024
|
Sep 2023
|
|
Total hash rate under management1 (EH/s) | 17.1 | 16.8 | 21.2 | |
- Proprietary hash rate
|
8.6
|
8.6
|
8.7
|
|
• Self-mining
|
8.1
|
7.8
|
7.2
|
|
• Cloud Hash Rate
|
0.5
|
0.8
|
1.5
|
|
- Hosting
|
8.5
|
8.2
|
12.5
|
|
Mining machines under management
|
167,000
|
167,000
|
221,000
|
|
- Self-owned2
|
87,000
|
87,000
|
92,000
|
|
- Hosted
|
78,000
|
80,000
|
129,000
|
|
Bitcoin mined (self-mining only)
|
164
|
166
|
482
|
• |
Self-mining refers to cryptocurrency mining for the Company’s own account, which allows it to directly capture the high
appreciation potential of cryptocurrency.
|
• |
Cloud Hash Rate offers hash rate subscription plans and shares mining income with customers under certain arrangements. The
Cloud Hash Rate stated above reflects the contracted hash rate with customers at month-end. However, throughout the month, the Cloud Hash Rate may transition to Self-mining hash rate if customers opt to not make their monthly electricity
payments for various reasons.
|
• |
Hosting encompasses a one-stop mining machine hosting solution including deployment, maintenance, and management services
for efficient cryptocurrency mining.
|
• |
Demolition work has been completed.
|
• |
Cooling system design completed and waiting to begin construction.
|
• |
First batch of cooling towers arrived at the site.
|
• |
Energization timeline to occur in phases between Q4 2024 and Q1 2025.
|
• |
Buildings and groundwork completed, along with the construction of the transformer foundation and housing.
|
• |
Orders for transformer and electrical equipment have been placed, with delivery and installation currently in progress. Additionally, the procurement and delivery of containers and hydro-cooling systems are underway, and drainage systems
construction is ongoing.
|
• |
Construction of the substation is ongoing and expected to be completed by the end of October 2024.
|
• |
Tydal, Norway Expansion Phase 1 of 40 MW remains on track to be energized by Q4 2024.
|
• |
Substation conceptual design is completed and long lead-time electrical equipment for the substation has been ordered.
|
• |
Engineering, Procurement, and Construction (EPC) contractor has been selected for the substation construction.
|
• |
Civil work is ongoing, with the majority expected to be completed by the end of Q4 2024 or Q1 2025.
|
• |
Building design is completed, and construction is anticipated to begin in Q4 2024, earlier than expected.
|
• |
Estimated energization timeline remains on track for mid-to-late 2025.
|
• |
Civil work is anticipated to be completed by the end of September 2024. Construction of transformer and container foundations is in progress and will be completed in phases, with the last phase expected by the end of February 2025.
|
• |
132kv/140MW and 220kv/360MW substation designs are completed with construction anticipated to be ready by the end of Q1 2025.
|
• |
Orders for the procurement of transformers and electrical equipment have been placed, with delivery and installation to be completed in phases over the next two quarters.
|
• |
Procurement and delivery of containers and hydro-cooling systems are in progress, with completion in phases by the end of Q1 2025.
|
Site / Location
|
Capacity (MW)
|
Status
|
Timing3
|
|
Electrical capacity
|
||||
- Rockdale, Texas
|
563
|
Online
|
Completed
|
|
- Knoxville, Tennessee
|
86
|
Online
|
Completed
|
|
- Wenatchee, Washington
|
13
|
Online
|
Completed
|
|
- Molde, Norway
|
84
|
Online
|
Completed
|
|
- Tydal, Norway
|
50
|
Online
|
Completed
|
|
- Gedu, Bhutan
|
100
|
Online
|
Completed
|
|
Total electrical capacity
|
8954
|
|||
Pipeline capacity
|
||||
40
|
In progress
|
Q4 2024
|
||
- Tydal, Norway Phase 2
|
135
|
In progress
|
Mid 2025
|
|
- Massillon, Ohio
|
221
|
In progress
|
Mid-to-late 2025
|
|
- Clarington, Ohio Phase 1
|
266
|
In progress
|
Q3 2025
|
|
- Clarington, Ohio Phase 2
|
304
|
Pending approval
|
Estimate 2026
|
|
- Jigmeling, Bhutan
|
500
|
In progress
|
Mid-to-late 2025
|
|
- Rockdale, Texas
|
179
|
In planning
|
Estimate 2026
|
|
Total pipeline capacity
|
1,645
|
|||
Total global electrical capacity
|
2,540
|
• |
October 24-25: Plan ₿ Forum in Lugano, Switzerland
|
• |
November 13-14: Cantor Crypto, Digital Assets & AI Infrastructure Conference in Miami, Florida
|
• |
November 20-21: North American Blockchain Summit in Dallas, Texas
|